Timber floor joists in progress

Wednesday, January 21, 2009


My workers have been installing the timber floor joists for the last few days. It is almost 60% completed. One of my readers asked me why I am using kelat for the 1st. Floor. The reason is the the Ground Floor is not a nesting area and thus it is not necessary to use red meranti. Besides kelat is slightly cheaper and harder than red meranti.