Ground beam and slab ready for concreting

Wednesday, December 3, 2008
0 comments
My workers had finished placing the steel reinforcement bars for the ground beams and the BRC for the suspended floors and they are ready to be concreted. I have booked the mobile crane for tomorrow. It will be used to lift the concrete to where it will be poured. With the reduction in fuel price, the operator had agreed to reduce the rental from Rm600 to Rm550 per day. This is still not back to the pre-petrol price hike rate which was RM450 per day.
Read more »

Reinforced Concrete Footing Completed

Monday, November 17, 2008
0 comments
Today, my workers managed to complete fixing the steel reinforcement for the footings and stumps. The mobile crane arrived as scheduled. My kepala managed to fix the water pump despite the initial hiccups and concreting started slightly late at around 11.00 a.m. Despite the late start, my workers with the cooperation of the crane operator managed to finish concreting all the 16 Nos. of footing by 5.00pm. What a feat and credit must go to the kepala and his gang of workers, altogether 6 of them. The crane rental was RM600 per day which is considered high because it was the rate when the diesel price was at its peak. I hope the government can do something to force the operators to reduce their rental.

After my workers finished concreting the footings at around 5.00pm, I noticed quite a number of swiftlets flying low below the tree tops inside my site and some hovering nearby as if acknowledging that this will be the BH to watch. Before this, the swiftlets used to fly pass above the tree tops.
Read more »

Excavation Works Started

Sunday, November 16, 2008
0 comments
Today the backhoe moved in to start excavating for the footings. Rental of the backhoe per day is RM400.00. The backhoe managed to complete excavating all the footings, totalling 16 Nos, and sizes ranging from 5' x 5' to 6' x 6'. At the same time my workers started to install the formworks and steel reinforcement for the footing and trying to get the footings ready for concreting tomorrow. Meanwhile, I had booked the mobile crane which will be used to place the concrete. I will be using site-mixed instead of ready-mixed because of space constraint. The mobile crane could not swing the boom outside because of my decision not to cut down trees unneccessarily.




Read more »
 